Knowledge / Architecture / Building services: plumbing, electrical and HVAC

Building services: plumbing, electrical and HVAC

Architecture (B.Arch) · Building technology · free study notes for exams, placements and interviews

In short

Building services are the water, waste, power, ventilation, air-conditioning, fire, gas and transport systems that make a building habitable - the "invisible" 25-40% of the project cost that an architect must plan space for at concept stage, not after. The architect sizes shafts, plant rooms, tank capacities, duct routes and toilet cores, and coordinates them with structure and finishes; detailed sizing is shared with plumbing, electrical and HVAC consultants. The governing document in India is the National Building Code of India 2016 (Part 8 Building Services, Part 9 Plumbing Services, Part 4 Fire and Life Safety), with IS codes, the Electricity Act 2003, CEA safety regulations and BEE energy codes layered on top. It is examined in B.Arch Building Services papers and in GATE-AR (services, NBC provisions, simple load and capacity calculations), and asked in every interview for architectural, MEP-coordination, project-management and green-building roles.

Explained

Scope, codes and design integration

Water supply and plumbing

Drainage, sanitation and waste water

Electrical services

HVAC and ventilation

Fire, gas and performance checks

Key points

Formulas and examples

Water demand Q = N × q, where N = number of users, q = lpcd (L/person/day); tank capacity in litres (1 m³ = 1,000 L)
Pump hydraulic power P = ρ g Q H (W), with ρ = 1,000 kg/m³, g = 9.81 m/s², Q in m³/s, H = total head in m; input power = P / (η_pump × η_motor)
Total head H = static lift + friction loss + residual pressure head
Manning (drains) V = (1/n) R2/3 S1/2; Q = A V; n ≈ 0.013 (uPVC/CI/cement-lined), R = A/P (= D/4 for a full circular pipe), S = slope
Hazen-Williams head loss h_f = 10.67 L Q1.852 / (C1.852 D4.87) (SI; C ≈ 140-150 for CPVC/uPVC, 100 for old GI)
Septic tank volume C = (P × q × t) + (P × s × n): P = users, q = sewage flow L/day, t = detention in days, s = sludge L/person/year, n = years between desludging
Rainwater harvest V = C × I × A: C = runoff coefficient (≈0.85 terrace), I = annual rainfall in m, A = catchment in m²
Three-phase power P = √3 V_L I_L cos φ; single-phase P = V I cos φ
Three-phase voltage drop ΔV = √3 I L (R cos φ + X sin φ), R and X in Ω/m; limit commonly 3-5% per IS 732
Capacitor rating kVAr = P (tan φ₁ − tan φ₂)
Cooling load Q = Q_sensible + Q_latent; TR = Q(kW)/3.517; COP = cooling output / power input
Supply air for sensible load: Q_s (kW) = 1.2 × V (m³/s) × ΔT (K) [ρc_p of air ≈ 1.2 kJ/m³·K]
Chilled water flow ṁ = Q / (c_p ΔT), c_p = 4.187 kJ/kg·K; 1 L/s ≈ 1 kg/s of water
Air changes per hour ACH = (air flow in m³/h) / room volume (m³)

Example 1 - Water demand, storage and pump for an apartment block. 60 flats × 4.5 persons = 270 persons at 135 lpcd.

Example 2 - Drain capacity and self-cleansing check. 100 mm uPVC drain at 1:60, n = 0.013.

Example 3 - Septic tank and rainwater harvesting. 20 users, q = 100 L/day, detention 1 day, sludge 30 L/person/year, desludged every 2 years.

Example 4 - Electrical load, cable drop and power factor. A floor panel feeds 50 kW at 0.85 pf on 415 V, 3-phase, 60 m away on 50 mm² copper (R ≈ 0.45 Ω/km, X ≈ 0.08 Ω/km at operating temperature).

Example 5 - Cooling load, tonnage and air flow for an office room. Sensible load 10 kW, latent 2.5 kW, 15 occupants.

Split / ductable DXVRFCentral chilled water
Typical rangeUp to about 20 TR10-200 TR per system100 TR and above
Part-load efficiencyPoor to moderateVery goodGood with VFDs and staging
Zoning and meteringPer unitExcellentPer AHU/FCU
Space neededOutdoor unit spaceOutdoor units + refrigerant pipesPlant room, cooling tower, shafts
Capital / running costLow / highMedium / lowHigh / lowest per TR
Maintenance skillLowMediumTrained operators, AMC
Best suited toResidences, small officesOffices, hotels, hospitals (mid-size)Malls, airports, campuses

Where it is used

Interview questions

Common mistakes