Knowledge / Placement essentials (aptitude, reasoning, verbal, communication, interviews, Excel, workplace) / Time and work

Time and work

Placement essentials (aptitude, reasoning, verbal, communication, interviews, Excel, workplace) (All) · Quantitative aptitude · free study notes for exams, placements and interviews

In short

Time and work problems convert "how long someone takes" into "how much is done per day", so that several workers' outputs can simply be added. One day's work is the reciprocal of the total time, so a person finishing a job in 10 days does 1/10 of it daily. The topic is standard in the quantitative-aptitude section of every Indian placement test (TCS NQT, Infosys, Wipro, Capgemini, Cognizant, Accenture), bank and SSC exams, and in B.Tech/BBA/MBA aptitude papers under CBCS. On the job the same arithmetic drives manpower planning, sprint velocity, shift staffing and project crashing — any question of the form "how many people for how many days".

Explained

Core idea: work as a rate

The LCM (total-work) method — preferred in exams

Standard question types

  1. Together time, given individual times — add rates (or units/day).
  2. One rate unknown — A and B together in 6 days, A alone in 10 → B's rate = 1/6 − 1/10 = 1/15 → 15 days.
  3. Pairwise data (A+B, B+C, C+A) — add all three pair rates and halve to get A+B+C; subtract a pair to isolate the third person.
  4. Someone leaves or joins midway — compute work done in the completed phase, then divide the remainder by the new rate.
  5. Alternate days — treat two days as one cycle; find work per cycle, count full cycles, finish the remainder carefully (the last part-day is not rounded up to a full day).
  6. Efficiency comparison — "A is 25% more efficient than B": rates 5 : 4, so times 4 : 5.
  7. Men, women, boys equivalence — convert all into one unit (say, man-equivalents) using the given relation.
  8. Wages and shares — wages are divided in the ratio of work actually done, which for equal working periods is the ratio of efficiencies.
  9. Contract / penalty problems — extra men are added to recover lost days; compute the shortfall and the required rate.
  10. Work-and-days with hours — bring hours per day into the chain rule.

Alternate days, and who starts first

Efficiency, wages and group-change problems

Assumptions, advantages and limitations

Key points

Formulas and examples

One day's work = 1 / (days to finish the whole job). Units: work in "jobs" or arbitrary units; time in days (or hours).
Combined rate R = 1/a + 1/b + 1/c + … ; Time together T = 1 / R
Two workers: T = ab / (a + b) days. Three workers: T = abc / (ab + bc + ca) days.
Chain rule: (M₁ × D₁ × H₁) / W₁ = (M₂ × D₂ × H₂) / W₂, where M = number of workers, D = days, H = hours per day, W = amount of work.
Efficiency ratio = inverse of time ratio: E_A / E_B = T_B / T_A
If A is x% more efficient than B: T_A / T_B = 100 / (100 + x)
Work left after t days = 1 − t × R ; Days to finish the rest = (work left) / (new rate)
Wages share of a worker ∝ (own rate) × (days worked) ; equivalently ∝ work done
With a spoiler: net rate = (sum of builders' rates) − (spoiler's rate)

Example 1 — Together, and one leaves midway. A can do a job in 20 days, B in 30 days. They start together; A leaves after 5 days. How long does B take to finish?

Example 2 — Pairwise rates. A and B together finish in 8 days, B and C in 12 days, C and A in 16 days. Find each one's time and the time for all three.

Example 3 — Efficiency and wages. A is 50% more efficient than B. Together they complete a job in 18 days and are paid ₹60,000 in total. Find B's time alone and each one's wage.

Example 4 — Chain rule with hours and a deadline. 15 workers working 8 hours a day build a wall in 12 days. The contractor must finish an identical wall in 9 days working 10 hours a day. How many workers are needed?

Example 5 — Alternate days with a spoiler. A builds a wall in 10 days; B (careless) demolishes it in 15 days. A works on day 1, B on day 2, alternately, A starting. When is the wall complete?

SituationModelQuick result
A: a days, B: b days, together1/a + 1/bab/(a+b) days
A+B given, A alone givensubtract rates1/(1/T_AB − 1/T_A)
A is k times as efficient as Brate ratio k : 1time ratio 1 : k
n workers, same rate, time T eachn/TT/n days
Spoiler presentsubtract spoiler's ratefinishes only if net rate > 0
Wages for unequal daysrate × days workedshare in that ratio

Where it is used

Interview questions

Common mistakes

Related topics

Open in the Knowledge reader →Find jobs →