Estimation and BOQ for interior projects

Interior Design (B.Des / B.Sc Interior) · Tools and estimation · free study notes for exams, placements and interviews

In short

Estimation is the process of working out, before work starts, how much material, labour and money an interior project will need; the Bill of Quantities (BOQ) is the itemised document that records each item of work, its unit, measured quantity, rate and amount. For interior projects the BOQ is both the pricing instrument (contractors quote against it) and the control document (site measurement, running bills and variations are checked against it). It matters because interiors are sold at a per-square-foot or lump-sum price while being built out of hundreds of separately-rated items — margin is won or lost in measurement rules and rate analysis, not in design. It is examined in B.Des / B.Sc Interior papers on "Estimation, Costing and Specification", in professional practice papers, and tested in almost every placement interview at design-build firms (Livspace, HomeLane, Design Cafe, Sleek, Godrej Interio, Bonito, Pepperfry Studio) and at contracting and PMC firms (Shapoorji, Leighton, CBRE, JLL, Colliers project management).

Explained

Estimate, BOQ and the documents around them

How an interior BOQ is structured

Units and modes of measurement

Rate analysis - building a rate from first principles

Step-by-step: preparing an interior BOQ

  1. Freeze drawings - layout, ceiling plan, electrical and plumbing plans, elevations, joinery details with sections, finish schedule.
  2. Create the item list section-wise from the drawings, with item codes; write specifications first, descriptions second.
  3. Take off quantities - measure systematically (room by room, then service by service), using the centre-line method for continuous partitions/skirting of uniform thickness and the long-wall-short-wall method otherwise; keep a take-off sheet showing No. × L × B × D so the arithmetic is auditable.
  4. Apply deductions for openings, cut-outs, pass-throughs as per IS 1200 / preambles.
  5. Add wastage and lap/overlap where the item is cut from sheets or rolls.
  6. Price it - rate analysis for bespoke items, SOR/market rates for standard items, vendor quotes for proprietary items (hardware, appliances, modular systems, lighting fixtures).
  7. Abstract - section totals, then add preliminaries, contingency (typically 3-5% of works; higher in renovation of an occupied space), design and PMC fee, escalation if the programme is long.
  8. Add taxes - GST on the works contract/supply, then issue for tender or client approval.
  9. Tender comparison - normalise the quotes (same quantities, same inclusions), prepare a comparative statement item-wise, flag abnormally low/high rates and unpriced items.
  10. Post-award - joint site measurement into the MB, RA bills by stage, variation orders priced from the BOQ rates for similar items (or by new rate analysis if the item is new), and a final bill with reconciliation statement.

Taxes, compliance and contract commercials

Key points

Formulas and examples

Amount for an item = Quantity × Rate (quantity in the stated unit; rate in ₹ per that unit)
Total project cost = Σ(Qty × Rate) + Preliminaries + Contingency + Design/PMC fee + Taxes
Unit rate R = [ M(1 + w) + L + P ] × (1 + o)
M = material cost per unit (₹), w = wastage fraction, L = labour cost per unit (₹), P = plant/tool/consumables per unit (₹), o = overhead + profit fraction
Carpet-area rate = Total interior cost ÷ Carpet area (₹/sft or ₹/sqm; state the area basis)
Centre-line method: Volume = Total centre-line length × thickness × height; Area (one face) = Total centre-line length × height, less corner correction
Corner correction for partitions of thickness t: subtract t/2 at each junction per overlapping wall
Boards required N = ceil[ Developed area × (1 + w) ÷ Area of one board ]
Standard plywood/board sheet = 8 ft × 4 ft = 32 sft = 2.973 sqm
Labour cost per unit L = Σ(number of persons × daily wage) ÷ daily output in units
Paint quantity = (Area × number of coats) ÷ spreading rate (sqm per litre), plus wastage
Depreciation/hire loading = Hire rate per day ÷ Units produced per day

Example 1 - Carcass rate analysis for a wardrobe (per sft of front elevation) Specification: 18 mm BWP plywood carcass, 1 mm inner laminate, 8 mm back, edge banding; assume 2.2 sft of board (developed, including shelves and partitions) per 1 sft of front elevation.

Example 2 - Flooring take-off with wastage and skirting Room 4.2 m × 3.6 m; 600 × 600 mm vitrified tile; 100 mm skirting on all four sides; one 0.9 m wide door opening (no skirting there).

Example 3 - Painting with a multiplying factor and deductions Wall 10.0 m long × 3.0 m high with one window 1.5 m × 1.2 m and one panelled door 1.0 m × 2.1 m (both painted separately); 2 coats of acrylic emulsion over primer.

Example 4 - Carpet-area rate and GST on a 2BHK turnkey fit-out Carpet area 950 sft. Works abstract: joinery ₹9,20,000; false ceiling and painting ₹2,10,000; electrical ₹1,45,000; flooring and tiling ₹1,70,000; loose furniture and soft furnishing ₹1,55,000.

Example 5 - Centre-line take-off for gypsum partitions A rectangular cabin block 6.0 m × 4.0 m is partitioned off an open floor by new 100 mm gypsum partitions on three sides (the fourth is an existing wall), height 2.85 m, with a 0.9 m × 2.1 m door.

BasisLump-sum / firm BOQItem-rate (measure and pay)Cost-plus
QuantitiesFixed at awardProvisional, re-measuredNot priced upfront
Risk of quantity errorContractorClientClient
SuitsComplete, frozen drawingsRenovation, evolving scopeFast-track, undefined scope
BillingStage payments on % completionMB measurement × BOQ rateActual cost + agreed fee
Variation handlingSeparate change orderBOQ rate applied to new quantityAbsorbed in actuals
ElementTypical unitMeasured asCommon deduction
Vitrified flooringsqmFinished floor areaNil for skirting; large voids deducted
False ceilingsqmPlan area of ceilingLarge openings and shafts
Gypsum partitionsqmElevation area, one sideDoor and window openings
Wardrobe carcasssft of front elevationWidth × height of the unitNil
Skirting / beadingRmRunning length along wallDoor openings
Wall paintingsqmNet wall areaOpenings beyond the stated small limit
Switches / fixturesnos.Count from electrical planNil
MS frameworkkgSection weight × lengthNil

Where it is used

Interview questions

Common mistakes

Related topics

Specification writing and materials for interiors · Modular furniture and joinery detailing · CAD, Revit and BIM for architects · Project management and site supervision for interiors · Professional practice, contracts and tendering · Building services and MEP coordination