In short

Business continuity planning (BCP) is the management discipline that keeps an organisation's critical business functions running, or restores them quickly, when a disruption hits; disaster recovery (DR) is the IT subset that restores systems, data and infrastructure. The two are measured by targets — RTO (how fast), RPO (how much data loss) and MTD (the absolute deadline) — derived from a business impact analysis. In India this is not optional for regulated sectors: RBI, SEBI and IRDAI mandate documented, tested continuity and recovery arrangements, and the Digital Personal Data Protection Act, 2023 makes safeguarding and breach notification a statutory duty from 13 May 2027 (until then IT Act s.43A and the SPDI Rules 2011 govern). It is examined in AICTE-model IT operations, cloud computing and information security papers, in UGC-CBCS cyber security courses, and asked in placement rounds at TCS, Infosys, Wipro, HCLTech, Cognizant, Accenture, Capgemini and every bank/NBFC IT team.

Explained

Definitions and how the pieces fit

Business impact analysis and risk assessment

  1. Inventory processes and the IT services behind them — map process → application → server/database → dependency (DNS, AD, payment gateway, SMS gateway).
  2. Quantify impact over time — financial loss, regulatory penalty, reputational damage, safety, at 1 h, 4 h, 1 day, 1 week.
  3. Set MTD/MTPD (maximum tolerable downtime / period of disruption) for each process — the point beyond which the business cannot recover.
  4. Derive RTO (must be less than MTD, leaving margin for business resumption) and RPO from data-change tolerance.
  5. Classify criticality: Tier 0/mission-critical (payments, core banking) → Tier 3 (internal reporting).
  6. Risk assessment (separate exercise): identify threats, likelihood and impact; risk = likelihood × impact; treat by avoid / reduce / transfer (insurance) / accept.
  7. Dependency and single-point-of-failure analysis — upstream vendors, a single ISP, one DBA who holds the keys, one AD forest.

Recovery objectives and metrics

Backup strategies and data protection

Recovery site strategies

Plan lifecycle, testing and governance

  1. Policy and scope — board/management approval, named BCM owner.
  2. BIA and risk assessment → recovery objectives.
  3. Strategy selection — site, backup, replication, vendor contracts with SLAs and penalties.
  4. Plan documentation — call trees, escalation matrix, RACI, restore runbooks, vendor contacts, declaration authority, alternate work locations. Keep a printed/offline copy; the plan must not live only on the system that fails.
  5. Testing, in increasing rigour: *checklist/desk review* → *walk-through/tabletop* (discussion of a scenario) → *simulation* → *parallel test* (DR runs alongside production, no cut-over) → *full-interruption test* (production actually moved — the only real proof, and the riskiest).
  6. Review and improvement — after every drill, incident and major change; at least annually, and after any significant change in architecture, regulation or vendors.
  7. Training and awareness — people, not documents, execute recovery.
  8. Indian regulatory and legal framework (verify current versions before quoting in an audit):
    • RBI — Cyber Security Framework for banks (2016 circular) and the Master Direction on Information Technology Governance, Risk, Controls and Assurance Practices, 2023 (effective 1 April 2024) require a board-approved BCP/DR policy, a DR site in a different seismic zone, DR drills at least half-yearly for critical systems, and defined RTO/RPO.
    • SEBI — Cybersecurity and Cyber Resilience Framework (CSCRF, 2024) for regulated entities; stock exchanges and depositories have long-standing BCP-DR norms with RTO of 45 minutes and RPO of 15 minutes for critical systems (confirm the current circular — these numbers have been revised over time).
    • IRDAI — information and cyber security guidelines require BCP/DR with periodic testing.
    • CERT-In Directions, 28 April 2022 — report specified cyber incidents within 6 hours of noticing, maintain ICT logs for 180 days in India.
    • Digital Personal Data Protection Act, 2023 — duty to protect personal data with reasonable security safeguards and to notify the Data Protection Board and affected data principals of a breach; Rules notified in 2025 with phased implementation, so check the stage in force.
    • IT Act, 2000 — section 43A/72A exposure for failure of reasonable security practices; ISO/IEC 27001:2022 control on ICT readiness for business continuity.
    • Telecom and insurance of records, plus NDMA/Disaster Management Act, 2005 for the national disaster framework; IS 1893 (Part 1):2016 for seismic zoning of the site.

Advantages, limitations and comparisons

Key points

Formulas and examples

Availability A = MTBF / (MTBF + MTTR) — dimensionless or %; MTBF = mean time between failures (h), MTTR = mean time to repair (h)
Annual downtime (minutes) = (1 − A) × 365 × 24 × 60
MTD = RTO + WRT — all in hours; WRT = work recovery time
Worst-case data loss ≈ backup/replication interval; RPO must be ≥ this interval
Cost of downtime = outage hours × revenue or loss per hour (₹/h)
SLE = Asset Value × Exposure Factor; ALE = SLE × ARO — SLE = single loss expectancy (₹), EF = fraction of asset lost, ARO = annual rate of occurrence (events/year)
Risk-justified DR spend ≤ ALE(without DR) − ALE(with DR)
Backup storage for a cycle ≈ F + (n × I) — F = full size (GB), I = daily incremental (GB), n = increments retained
RAID 5 usable capacity = (N − 1) × disk size; RAID 6 = (N − 2) × disk size; RAID 10 = (N/2) × disk size

Example 1 — Availability and downtime. A server has MTBF 4,000 h and MTTR 5 h.

Example 2 — RPO, RTO and cost of downtime. A bank's internet-banking platform earns ₹25 lakh revenue per hour. Nightly backup at 01:00; failure at 16:00; restore takes 6 h.

Example 3 — ALE and DR justification. A data centre worth ₹8 crore faces a flood that would destroy 40% of its value, expected once in 20 years.

Example 4 — Backup window and storage. A 2 TB file server changes 3% daily. Full backup throughput 200 GB/h; retention = 1 full + 6 incrementals (GFS weekly cycle).

Example 5 — MTD arithmetic. A hospital's billing system has MTD 8 h. Restoring the VM and database takes 3 h; re-keying manual bills raised during the outage takes 4 h.

StrategyTypical RTOTypical RPORelative cost
Tape/off-site backup onlyDaysUp to 24 hLowest
Cold siteDays to weeksUp to 24 hLow
Warm site / pilot light4–24 hMinutes to hoursMedium
Hot site / warm standby (async)Minutes to 4 hSeconds to minutesHigh
Active-active mirrored (sync)Near zeroZeroHighest
AvailabilityDowntime per yearDowntime per month
99% (two nines)3.65 days7.31 h
99.9%8.76 h43.8 min
99.99%52.6 min4.38 min
99.999%5.26 min26.3 s
FullIncrementalDifferential
Data copiedAllChanged since last backupChanged since last full
Backup windowLongestShortestMedium
Storage usedHighestLowestMedium
Restore chain1 setFull + all incrementsFull + latest differential

Where it is used

Interview questions

Common mistakes

Related topics

Virtualisation: VMware and Hyper-V · Cloud computing service and deployment models · Information security management and ISO/IEC 27001 · RAID, storage area networks and data centre design · Network design, load balancing and DNS failover · IT service management and ITIL incident/problem management

Open in the Knowledge reader →Find jobs →