Knowledge / Production and Industrial Engineering / Statistical quality control

Statistical quality control

Production and Industrial Engineering (B.E./B.Tech) · Quality and reliability · free study notes for exams, placements and interviews

In short

Statistical quality control (SQC) is the use of statistics to judge whether a manufacturing process is behaving consistently and whether its output meets specification. Its three arms are process control (control charts), process capability analysis (Cp, Cpk) and acceptance sampling (lot-by-lot inspection plans). It rests on Shewhart's distinction between chance (common) causes that are inherent in the process and assignable (special) causes that can be found and removed. It is examined in GATE PI and ME (industrial engineering section), in university Quality Control / Quality Assurance and Reliability papers, and is used daily by quality engineers at Maruti Suzuki, Bosch, Tata Motors, Sundram Fasteners, TVS, Bharat Forge, Cipla and Sun Pharma, and by every IATF 16949 or ISO 13485 supplier audited on SPC evidence.

Explained

Variation, causes and the basic logic

Control charts for variables (measured data)

Control charts for attributes (counted data)

Reading a chart: out-of-control rules

Process capability and performance

Acceptance sampling

Related techniques and Indian practice

Key points

Formulas and examples

X̄ chart: CL = X̄̄, UCL/LCL = X̄̄ ± A₂·R̄ (units of the characteristic, e.g. mm)
R chart: CL = R̄, UCL = D₄·R̄, LCL = D₃·R̄ (D₃ = 0 for n ≤ 6)
s chart: CL = s̄, UCL = B₄·s̄, LCL = B₃·s̄; X̄ limits = X̄̄ ± A₃·s̄
σ estimate: σ̂ = R̄/d₂ = s̄/c₄ (same units as the measurement)
p chart: CL = p̄, limits = p̄ ± 3√[p̄(1−p̄)/n]; p̄ = total defectives / total inspected (dimensionless fraction)
np chart: CL = n·p̄, limits = n·p̄ ± 3√[n·p̄(1−p̄)] (count of items)
c chart: CL = c̄, limits = c̄ ± 3√c̄ (count of defects per inspection unit)
u chart: u = c/n, CL = ū, limits = ū ± 3√(ū/nᵢ) (defects per unit; nᵢ = units in sample i)
Negative LCL is reported as 0.
Cp = (USL − LSL)/(6σ); Cpu = (USL − μ)/(3σ), Cpl = (μ − LSL)/(3σ), Cpk = min(Cpu, Cpl)
k (off-centre) = |target − μ| / [(USL − LSL)/2]; Cpk = Cp(1 − k)
Cpm = Cp / √[1 + ((μ − T)/σ)²], T = target
Pp, Ppk: same formulae with overall σ of all individuals; fraction out of spec = Φ(−Cpl·3) + Φ(−Cpu·3)
Sigma level ≈ 3·Cpk + 1.5 (long-term convention)
Single sampling, binomial: Pa = Σ_{d=0}^{c} ⁿC_d pd (1−p)^{n−d}
Poisson approximation (n large, p small): Pa = Σ_{d=0}^{c} e^{−np}(np)d / d!
AOQ ≈ p·Pa·(N−n)/N ≈ p·Pa; ATI = n + (1−Pa)(N−n) (average total inspected per lot)
ARL (in control) = 1/α; ARL (shifted) = 1/(1−β)

Constants used below (standard SQC tables): n = 5 → A₂ = 0.577, D₃ = 0, D₄ = 2.114, d₂ = 2.326, A₃ = 1.427, c₄ = 0.9400.

Example 1 — X̄ – R chart limits. A shaft diameter is measured in 25 subgroups of n = 5. ΣX̄ = 1,250.0 mm over 25 subgroups and ΣR = 1.00 mm.

Example 2 — capability of the same process. Specification 50.00 ± 0.05 mm (USL 50.05, LSL 49.95), process mean 50.01 mm, σ̂ = 0.0172 mm.

Example 3 — p chart with varying sample size. 20 daily samples of about 400 castings each, giving 8,000 inspected in total with 240 defectives found.

Example 4 — c chart. Enamelled refrigerator doors inspected for paint blemishes; 30 doors give 120 blemishes in total.

Example 5 — single sampling plan and OC curve. Lot N = 2,000, plan n = 80, c = 2. Compute Pa at p = 1% and p = 4% (Poisson approximation).

FeatureVariables chart (X̄–R)Attributes chart (p, c)
DataMeasured valueCount / classification
Sample sizeSmall (4–5)Large (50–400+)
InformationMean and spread separatelyOnly proportion or defect rate
SensitivityHigh — detects drift earlyLow — needs a bigger shift
Inspection costHigher (gauges, skill, time)Lower (go/no-go)
Charts neededOne pair per characteristicOne chart can cover many characteristics
Gives capability?Yes (Cp, Cpk)No
IndexUsesCentring counted?Typical target
CpShort-term σ (R̄/d₂)No≥ 1.33
CpkShort-term σYes≥ 1.33 (1.67 new/critical)
CpmShort-term σ + targetYes, against target≥ 1.33
Pp / PpkLong-term overall σPp no, Ppk yes≥ 1.33

Where it is used

Interview questions

Common mistakes

Related topics

Lean manufacturing and Six Sigma · Reliability engineering · ISO 9001 quality management systems · Total productive maintenance · Design of experiments and Taguchi methods · Probability and statistics for engineers