Knowledge / Business Administration / Project management

Project management

Business Administration (BBA/BMS) · Operations · free study notes for exams, placements and interviews

In short

Project management is the application of knowledge, skills, tools and techniques to a temporary, unique undertaking so that it is delivered within scope, time, cost and quality limits. It matters because every organisation runs change through projects - a plant expansion, an ERP rollout, a new branch, a product launch - and most overruns are planning failures, not technical ones. In BBA/BMS Operations papers it carries a full question (life cycle, WBS, CPM/PERT networks, crashing, Gantt), and in placements it appears as network problems in aptitude rounds and as "tell me how you would plan this" in interviews for roles at L&T, Tata Projects, Infosys, TCS, Accenture, Capgemini and PMO teams across BFSI.

Explained

What a project is, and the triple constraint

Project life cycle and processes

  1. Initiation - identify need, feasibility study, stakeholder identification, project charter (authorises the project and names the PM).
  2. Planning - scope statement, WBS, activity list, network and schedule, budget, risk register, quality plan, procurement plan, communication plan.
  3. Execution - acquire and direct the team, do the work, manage vendors and quality.
  4. Monitoring and control - track time, cost and scope; change control to stop scope creep; corrective action.
  5. Closure - handover, final accounts, release of resources, lessons learned document.
  6. Work Breakdown Structure (WBS): hierarchical decomposition of the deliverable into work packages small enough to estimate and assign; the 100% rule says the WBS must contain all the work and nothing more. A RACI chart (Responsible, Accountable, Consulted, Informed) assigns the work packages.
  7. Risk management: identify, assess (probability × impact), respond (avoid, mitigate, transfer - typically through insurance or a fixed-price contract - or accept), monitor. Contingency reserve covers known risks; management reserve covers unknown ones.

Network techniques - CPM and PERT

Project cost and performance control

Key points

Formulas and examples

PERT expected time: tE = (a + 4m + b)/6, variance σ² = ((b − a)/6)²; a, m, b in days (weeks)
Project SD: σp = √(sum of σ² of critical activities); Z = (TS − TE)/σp, TS = scheduled (target) time, TE = expected project time
Total float TF = LS − ES = LF − EF; Free float FF = ES(successor) − EF(activity)
Cost slope = (crash cost − normal cost) / (normal time − crash time), in ₹ per day
Total project cost = direct cost + indirect cost (indirect = rate ₹/day × duration)
EVM: SV = EV − PV; CV = EV − AC; SPI = EV/PV; CPI = EV/AC; EAC = BAC/CPI (BAC = budget at completion, ₹)

Example 1 - PERT: expected time, variance and probability A project has three activities in series on its only path:

ActivityambtE = (a+4m+b)/6σ² = ((b−a)/6)²
A4614(4+24+14)/6 = 7(10/6)² = 2.78
B6918(6+36+18)/6 = 10(12/6)² = 4.00
C258(2+20+8)/6 = 5(6/6)² = 1.00

Example 2 - Crashing to least total cost A project of 5 activities has a critical path A → B → C of 20 days. Indirect cost is ₹8,000 per day.

ActivityNormal time (d)Normal cost (₹)Crash time (d)Crash cost (₹)Cost slope (₹/d)
A650,000462,0006,000
B870,000594,0008,000
C640,000460,00010,000

Where it is used

Interview questions

Common mistakes

Related topics