Knowledge / Commerce (General / Accounting and Finance / Banking and Insurance) / Budgeting and standard costing

Budgeting and standard costing

Commerce (General / Accounting and Finance / Banking and Insurance) (B.Com) · Cost and management accounting · free study notes for exams, placements and interviews

In short

Budgeting is the process of expressing a firm's plans for a future period in quantitative and monetary terms, and budgetary control is the use of those budgets to compare actual results, isolate differences and fix responsibility. Standard costing goes one level deeper: it sets a predetermined cost per unit of output and analyses the difference between standard and actual cost into named variances (price, usage, rate, efficiency, volume) so that the cause and the responsible manager can be identified. The two are the core "control" half of management accounting — planning in advance and explaining the gap afterwards. In B.Com and M.Com papers this is usually the heaviest-scoring chapter (cash budget, flexible budget and full variance sets), and it recurs in CA/CMA Inter, UGC-NET Commerce and placement tests for FP&A, costing, internal audit and shared-service roles at firms such as ITC, Asian Paints, Tata Steel, Hindustan Unilever, Maruti Suzuki, Genpact, Deloitte and the Big 4 GCCs.

Explained

Budget, budgetary control and the framework

Functional budgets and the master budget

Fixed, flexible and modern techniques

Standard costing: standards and the standard hour

Variance analysis — material, labour and overhead

Sales variances, profit reconciliation and control ratios

BasisBudgetary controlStandard costing
ScopeWhole organisation, all functions including capital and cashMainly manufacturing/operating cost per unit
Unit of measureTotal amounts for a department or periodCost per unit of product or service
Based onExpected (attainable) performancePredetermined scientific standards
Variance detailBroad, by cost headDetailed, split into price/usage/rate/efficiency
Needs the other?Can exist without standard costingWorks best with budgets; needs cost standards
Intensity of useProjection and policy toolDay-to-day operating control tool

Key points

Formulas and examples

Production budget (units) = Budgeted sales + Closing finished stock − Opening finished stock
Purchase budget (qty) = Material for production + Closing material stock − Opening material stock
Flexible budget cost at X units = Fixed cost + (Variable cost per unit × X); semi-variable split by high-low: variable rate = (Cost at high − Cost at low) ÷ (Units high − Units low)
Closing cash = Opening cash + Receipts − Payments (₹)
Material cost variance MCV = (SQ × SP) − (AQ × AP) [SQ = standard qty for *actual output*]
Material price variance = AQ × (SP − AP); Material usage variance = SP × (SQ − AQ)
Material mix variance = SP × (RAQ − AQ), where RAQ = total actual input in standard proportion
Material yield variance = Std cost per unit of output × (Actual output − Standard output from actual input)
Labour cost variance = (SH × SR) − (AH paid × AR); Rate variance = AH paid × (SR − AR)
Idle time variance = Idle hours × SR (always adverse); Efficiency variance = SR × (SH − AH worked)
Variable OH cost variance = (SH × Std VOH rate) − Actual VOH; Expenditure = (AH × Std rate) − Actual VOH; Efficiency = Std rate × (SH − AH)
Fixed OH cost variance = (SH × Std FOH rate) − Actual FOH; Expenditure = Budgeted FOH − Actual FOH
Fixed OH volume variance = (SH × Std rate) − Budgeted FOH; Efficiency = Std rate × (SH − AH); Capacity = Std rate × (AH − Revised budgeted hours); Calendar = Std rate per day × (Actual days − Budgeted days)
Sales price variance = AQ × (AP − SP); Sales volume variance = SP × (AQ − BQ)
Sales margin price variance = AQ × (Actual margin − Std margin); Sales margin volume variance = Std margin × (AQ − BQ)
Efficiency ratio = (Std hours for actual output ÷ Actual hours worked) × 100
Capacity ratio = (Actual hours worked ÷ Budgeted hours) × 100
Activity ratio = (Std hours for actual output ÷ Budgeted hours) × 100 = Capacity × Efficiency

Symbols: S = standard, A = actual, B = budgeted, Q = quantity, P = price, H = hours, R = rate; quantities in kg or units, hours in labour/machine hours, money in ₹.

Example 1 — Material variances with mix and yield. Standard for 100 kg of output: A 60 kg @ ₹20 = ₹1,200; B 50 kg @ ₹10 = ₹500; input 110 kg, standard cost ₹1,700 per 100 kg output (₹17 per kg of output). Actual output 1,000 kg from A 640 kg @ ₹22 and B 540 kg @ ₹9.

Example 2 — Labour variances and control ratios. Standard 5 hours @ ₹40 = ₹200 per unit; budget 1,100 units (5,500 hours). Actual output 1,000 units; hours paid 5,400 including 150 idle hours; wages ₹2,32,200 (actual rate ₹43).

Example 3 — Overhead variances (four-way). Budget: 2,000 units, 10,000 hours, 25 working days, fixed OH ₹2,00,000 (₹20/hour, ₹8,000/day), variable OH ₹1,00,000 (₹10/hour). Actual: 1,900 units, 9,300 hours, 24 days, fixed OH ₹2,06,000, variable OH ₹96,000. Standard hours for actual output = 9,500.

Example 4 — Flexible budget. 100% capacity = 10,000 units. Material ₹60/unit, labour ₹40/unit, variable OH ₹20/unit; semi-variable OH ₹1,50,000 at 100% (60% fixed → ₹90,000 fixed, ₹6/unit variable); fixed OH ₹2,00,000.

Item (₹)70% – 7,000 u85% – 8,500 u100% – 10,000 u
Direct material4,20,0005,10,0006,00,000
Direct labour2,80,0003,40,0004,00,000
Variable overhead1,40,0001,70,0002,00,000
Semi-variable (90,000 + ₹6/u)1,32,0001,41,0001,50,000
Fixed overhead2,00,0002,00,0002,00,000
Total cost11,72,00013,61,00015,50,000
Cost per unit167.43160.12155.00

Example 5 — Cash budget (March and April). Sales: Feb ₹5,00,000, Mar ₹6,00,000, Apr ₹5,50,000. Collections 40% in the month of sale, 60% next month. Purchases = 60% of next month's sales, paid one month after purchase. Wages ₹50,000 paid in the same month; overheads ₹30,000 paid in the following month. Opening cash 1 March ₹80,000; machine bought in March for ₹2,00,000.

Where it is used

Interview questions

Common mistakes

Related topics