Knowledge / Civil Engineering / Estimation and costing

Estimation and costing

Civil Engineering (B.E./B.Tech) · Construction management · free study notes for exams, placements and interviews

In short

Estimation is the calculation of probable quantities of materials, labour, equipment and money needed to complete a construction project before it is built; costing is the assignment of rates and money values to those quantities. A detailed estimate supports administrative approval, technical sanction, budgeting, tender invitation, contractor bidding, running-account payments and final-bill settlement. Indian practice follows IS 1200 (method of measurement of building and civil engineering works, in 28 parts), IS 3861 (plinth, carpet and rentable area of buildings), CPWD/State PWD Delhi Schedule of Rates (DSR) and departmental works manuals. It is examined in university Construction Management/Estimation papers, in GATE Civil (Construction Materials and Management), and in the technical rounds of L&T, Tata Projects, Shapoorji Pallonji, NBCC, CPWD, PWD, MES, RITES, NHAI and metro-rail recruitment, where quantity take-off and rate build-up are asked directly.

Explained

Purpose, data needed and types of estimate

Parts of a detailed estimate and the standard allowances

  1. Report — scope, basis, specifications adopted, rate source.
  2. General specifications and detailed specifications.
  3. Measurement sheet (details of measurement) — item, number, length, breadth, height, quantity.
  4. Abstract of estimated cost — quantity × rate = amount, item by item.
  5. Drawings, lead statement, analysis of rates (where no scheduled rate exists).
  6. Contingencies: 3-5% of the estimated cost for unforeseen petty items; 5% is customary in PWD practice.
  7. Work-charged establishment: about 1.5-2% for site staff paid from the work's funds.
  8. Other provisions commonly added: tools and plant (T&P) 1-1.5%, centage/departmental charges (for deposit works, often of the order of 10-15% depending on the department's rules), petty supervision charges, and price escalation/contingency for price rise where the period is long.
  9. Taxes: works contracts attract GST (as of now, composite works contracts for most government/infrastructure work are taxed at 18%, with concessional rates for a few specified categories; rates are notified and revised, so the current notification governs). Estimates state clearly whether rates are inclusive or exclusive of GST.

Units of measurement and the rules of IS 1200

Methods of taking out quantities for buildings

Rates, cost structure and economics of an item

Depreciation, valuation and life-cycle cost

Key points

Formulas and examples

Plinth area estimate: Cost = Plinth area (m²) × Plinth area rate (₹/m²)
Cubical content estimate: Cost = Plinth area (m²) × Height (m) × Rate (₹/m³)
Updated cost = Old cost × (Current cost index / Base cost index)
Centre line length for deduction: L_eff = ΣL_cl − (number of junctions × half breadth of layer)
Long wall length (out-to-out) = c/c length + breadth of layer; Short wall length (in-to-in) = c/c length − breadth of layer
Volume of a layer = Length × Breadth × Depth (m³)
Unit mass of round steel bar w = d²/162.2 kg/m (d in mm), from density 7,850 kg/m³
Trapezoidal (average end area): V = L × (A₁ + A₂)/2; Prismoidal: V = (L/6)(A₁ + 4A_m + A₂)
Earthwork of a road section (level ground, side slope 1:s): A = B·d + s·d² (B = formation width, d = depth)
Total estimate = Σ(Quantity × Rate) + Contingencies + Work-charged establishment + Other charges
Straight-line depreciation: D = (C − S)/n; Book value after m years = C − mD
Declining balance: Value after m years = C(1 − r)m
Sinking fund annual instalment: I = (C − S) × i / [(1 + i)n − 1]
Capitalised value = Net annual income × Year's purchase; YP (perpetuity) = 100/rate of interest (%)
Year's purchase for a limited (terminable) income of n years = [1 − (1 + i)−n]/i

Example 1 - Approximate estimate by plinth area, with all allowances A two-storeyed office building has a plinth area of 320 m² per floor. The plinth area rate adopted is ₹18,500/m². Provide contingencies at 5%, work-charged establishment at 2% and T&P at 1%.

Example 2 - Centre line method for a single-room building Room internal size 5.00 m × 4.00 m, superstructure walls 300 mm thick (one brick in cement mortar), height 3.20 m above plinth. Foundation: concrete bed 900 mm wide × 300 mm deep; one footing course 600 mm wide × 400 mm deep; plinth masonry 300 mm wide × 600 mm high. No cross walls.

Example 3 - Plastering with the IS 1200 deduction rule Plaster both faces of the above room's walls (12 mm thick, 1:6 cement mortar), internal height 3.20 m, same openings. Treat each opening by the IS 1200 rule.

Example 4 - Road earthwork by average end area and prismoidal formula A road embankment has formation width 10 m, side slopes 1:2 (s = 2). Centre heights at three chainages 30 m apart are 1.00 m, 1.50 m and 2.00 m; ground is level transversely.

Example 5 - Steel quantity and depreciation/valuation (a) A slab needs 120 bars of 12 mm, each 4.60 m long, and 80 bars of 10 mm, each 3.40 m long.

(b) A building cost ₹60,00,000 to construct, has a useful life of 60 years and a scrap value of 10% of cost.

BasisApproximate estimateDetailed estimate
Input neededLine plan, past ratesComplete working drawings, specifications, SOR
Unit of workingm², m³, service unitEach item of work in its own unit
Time to prepareHoursDays to weeks
Typical accuracy±15-20%About ±5%
Used forFeasibility, administrative approval, budget provisionTechnical sanction, tender BOQ, payments
MethodCentre lineLong wall-short wall
Length usedOne c/c length for all layersSeparate lengths per layer
Cross wallsDeduct half breadth per junctionHandled automatically by out-to-out/in-to-in
Best forUniform wall thickness, symmetrical plansWalls of differing thickness, irregular plans
Error riskMissing a junction deductionWrong length at each change of thickness

Where it is used

Interview questions

Common mistakes

Related topics

Quantity surveying and rate analysis · Contracts, tenders and specifications · Project planning: CPM and PERT · Equipment management and productivity · Real estate development and RERA · AutoCAD, STAAD.Pro and BIM basics

Open in the Knowledge reader →Find jobs →