Knowledge / Civil Engineering / Project planning: CPM and PERT

Project planning: CPM and PERT

Civil Engineering (B.E./B.Tech) · Construction management · free study notes for exams, placements and interviews

In short

CPM (Critical Path Method) and PERT (Programme Evaluation and Review Technique) are network-based planning techniques that break a project into activities, link them by dependency, and compute the shortest possible completion time and the slack available on every activity. CPM assumes a single deterministic duration per activity and is used for repetitive construction work; PERT uses three time estimates and gives the probability of finishing by a target date, so it suits research-type or first-of-a-kind work. For a civil engineer they decide when materials, formwork, labour gangs and payments are mobilised, and they are the technical basis of delay claims and extension-of-time disputes. The topic carries guaranteed marks in GATE Civil (floats, cost slope, PERT probability) and university construction-management papers, and it is asked in planning-engineer interviews at L&T, Tata Projects, Afcons, Shapoorji Pallonji, NCC, NHAI/DMRC consultancies and PMC firms, where Primavera P6 and MS Project are the working tools.

Explained

From bar charts to networks

Network rules, AoA and AoN

CPM time analysis: passes, floats and the critical path

  1. Forward pass (earliest times), starting at zero: ES of an activity = largest EF of its predecessors; EF = ES + D. In AoA, earliest event time Ej = max(Ei + Dij). The final value is the project duration.
  2. Backward pass (latest times), starting with LF of the last activity = project duration: LF = smallest LS of its successors; LS = LF − D. In AoA, Li = min(Lj − Dij).
  3. Event slack = Li − Ei. A critical event has zero slack; a critical activity has zero total float and lies on a chain of critical events.
  4. Critical path: the continuous chain from start to finish with zero total float; it is the longest path in time, and it fixes the project duration. There may be more than one critical path; a path with small float is sub-critical and must be watched.
  5. Total float TF = LS − ES = LF − EF. The delay an activity can absorb without delaying the project (but it eats into successors' float).
  6. Free float FF = min(ES of successors) − EF (in AoA, FF = TF − slack of head event). Delay available without disturbing the early start of any following activity.
  7. Independent float IF = ES of successor − LF of predecessor − D, taken as zero if negative (in AoA, IF = FF − slack of tail event). Float available even if predecessors finish as late as possible and successors start as early as possible.
  8. Interfering float = TF − FF — the part of the float that, if used, pushes successors later.
  9. Always TF ≥ FF ≥ IF. Float on a path is shared: once one activity consumes it, the others on that path lose it.
  10. Advantages of CPM: pinpoints controlling activities, quantifies the effect of a delay, supports resource and cash planning, and gives a defensible record for claims. Limitations: needs reliable durations and complete logic; a network is only as good as its assumptions; it ignores resource limits unless levelling is done; and it is activity-based, so continuous repetitive work (pipelines, housing blocks) is often better shown by Line of Balance (LOB).

PERT: three time estimates and probability

Precedence networks, leads and lags

Time–cost trade-off and crashing

Resources, monitoring, updating and Indian practice

Key points

Formulas and examples

EF = ES + D · LS = LF − D · ES = max(EF of predecessors) · LF = min(LS of successors) — all in time units (days/weeks)
Earliest event time Ej = max(Ei + Dij); Latest event time Li = min(Lj − Dij); Event slack = Li − Ei
Total float TF = LS − ES = LF − EF
Free float FF = min(ES of successors) − EF (= TF − head-event slack)
Independent float IF = max[0, (min ES of successors − max LF of predecessors − D)] (= FF − tail-event slack)
Interfering float = TF − FF
Expected time te = (to + 4tm + tp)/6; Std deviation σ = (tp − to)/6; Variance σ² = [(tp − to)/6]²
Expected project duration Te = Σ te (along critical path); σ_path = √(Σ σ² of critical activities)
Probability variate Z = (Ts − Te)/σ_path (Ts = scheduled/target date); probability read from standard normal table
Cost slope = (Cc − Cn)/(Tn − Tc) in ₹/day (Cn, Cc = normal and crash cost; Tn, Tc = normal and crash time)
Total project cost = Σ direct costs + (indirect cost per day × project duration)

Example 1 — CPM: critical path and all three floats (AoN)

ActivityPredecessorD (days)ESEFLSLFTFFFIF
A—40404000
B—60639333
CA54949000
DA347912500
EB, C7916916000
FD47111216550
GE, F316191619000

Example 2 — CPM on an AoA network: event times and slack

Activities (i–j, duration in weeks): 1–2 = 3, 1–3 = 5, 2–4 = 7, 3–4 = 4, 3–5 = 6, 4–6 = 5, 5–6 = 2.

Example 3 — PERT: expected duration and probability

Critical path activities P–Q–R–S (in series):

Activitytotmtpte = (to+4tm+tp)/6σ = (tp−to)/6σ²
P251462.004
Q36961.001
R471682.004
S14741.001

Example 4 — Crashing to the optimum duration

Three activities in series; indirect cost ₹14,000 per day.

ActivityTn (d)Cn (₹)Tc (d)Cc (₹)Cost slope (₹/day)
A660,000480,00010,000
B880,00061,04,00012,000
C550,000465,00015,000

CPM versus PERT

CPMPERT
Duration estimateSingle, deterministicThree estimates, beta distribution
OrientationActivity-orientedEvent-oriented
Suited toRepetitive, well-understood work (buildings, roads)Novel, uncertain work (R&D, first-of-kind)
OutputDuration, floats, time–cost trade-offExpected duration and probability of meeting a date
Cost handlingCrashing and optimum cost built inOriginally time only
Control focusCritical activities and floatEvent slack and probability

Where it is used