Knowledge / Electrical and Electronics Engineering / Economic dispatch and unit commitment

Economic dispatch and unit commitment

Electrical and Electronics Engineering (B.E./B.Tech) · Power systems · free study notes for exams, placements and interviews

In short

Economic dispatch (ED) decides how much each already-running generator should produce so that the total fuel cost of meeting the load is minimum, while unit commitment (UC) decides which units should be running at all over the next hours or day, including when to start and stop them. ED works in seconds to minutes within fixed commitment; UC works over 24 hours to a week and must respect start-up costs, minimum up/down times and reserve requirements. Both are core to load despatch centre operation — Grid-India (NLDC/RLDCs) and the State Load Despatch Centres run merit order dispatch under the Indian Electricity Grid Code, with Security Constrained Economic Dispatch run by Grid-India for inter-State stations. The topic is a reliable source of numerical questions in GATE (EE), university power systems papers, and in interviews at NTPC, POWERGRID, Grid-India, state transcos/gencos, Tata Power, Adani and energy-analytics firms.

Explained

Cost curves and the dispatch problem

Economic dispatch neglecting losses — the equal incremental cost criterion

Economic dispatch including transmission losses

Constraints and solution methods for ED

Unit commitment — the problem and its constraints

Unit commitment solution methods

Indian practice: merit order, SCED and the regulatory frame

Key points

Formulas and examples

F_i(P_i) = a_i + b_i P_i + c_i P_i² — fuel cost, ₹/h; P in MW; a in ₹/h, b in ₹/MWh, c in ₹/MW²h
IC_i = dF_i/dP_i = b_i + 2c_i P_i — incremental fuel cost, ₹/MWh
Equal-λ (lossless): dF₁/dP₁ = dF₂/dP₂ = … = λ, with Σ P_i = P_D
Direct solution: P_i = (λ − b_i)/(2c_i); λ = [P_D + Σ(b_i/2c_i)] / Σ(1/2c_i)
With losses: dF_i/dP_i + λ(∂P_L/∂P_i) = λ ⇒ L_i (dF_i/dP_i) = λ, L_i = 1/(1 − ∂P_L/∂P_i)
Loss formula: P_L = Σ_i Σ_j P_i B_ij P_j ; ∂P_L/∂P_i = 2 Σ_j B_ij P_j (B_ij in MW⁻¹)
Variable cost (₹/MWh) = [Station heat rate (kcal/kWh) ÷ GCV (kcal/kg)] × fuel price (₹/kg) × 1000
Start-up: cooling C = C_c(1 − e−t/α) + C_f ; banking C = C_b t + C_f (t = hours off, α = thermal time constant in h)
Full-load average cost FLAC = F(P_max)/P_max (₹/MWh) — priority-list ranking
UC search space ≤ (2N − 1)T ; ramp limit: |P_i(t) − P_i(t−1)| ≤ R_i × Δt
Forward DP: F_cost(K,I) = min_L [ P_cost(K,I) + S_cost(K−1,L : K,I) + F_cost(K−1,L) ]

Example 1 — Variable cost for merit order. A coal unit has station heat rate 2,450 kcal/kWh, coal GCV 3,500 kcal/kg, delivered coal price ₹4,200/tonne (= ₹4.20/kg).

Example 2 — Two-unit economic dispatch, no losses. F₁ = 0.2P₁² + 1800P₁ + 250,000 ₹/h; F₂ = 0.3P₂² + 1900P₂ + 180,000 ₹/h; P_D = 600 MW.

Example 3 — Same system with a generation limit. Now P₁,max = 400 MW.

Example 4 — Loss coordination with penalty factors. Same cost curves. Total generation 600 MW meets a load of 580 MW plus 20 MW of losses, with ∂P_L/∂P₁ = 0.05 and ∂P_L/∂P₂ = 0.

Example 5 — B-coefficients. B₁₁ = 1.0×10⁻⁴, B₁₂ = B₂₁ = 0.5×10⁻⁴, B₂₂ = 3.0×10⁻⁴ MW⁻¹, with P₁ = 300 MW, P₂ = 200 MW.

Example 6 — Priority-list unit commitment over 3 hours.

UnitP_min/P_max (MW)No-load (₹/h)Incremental (₹/MWh)Start-up (₹)FLAC (₹/MWh)
A150 / 5002,00,0001,9004,00,0002,300
B100 / 3001,20,0002,1002,50,0002,500
C50 / 15060,0003,20080,0003,600

Priority order A → B → C. Loads: 450, 700, 900 MW; only A is initially on.

Example 7 — Banking versus cooling. C_c = ₹5,00,000, α = 5 h, C_b = ₹80,000/h, C_f = ₹50,000.

Economic dispatchUnit commitment
DecisionHow much each running unit generates (continuous)Which units run (binary) + dispatch
HorizonSeconds to 15 minHours to one week
Key costIncremental fuel costStart-up + no-load + fuel
Key constraintsP_min/P_max, ramp, losses, line flowsReserve, min up/down time, crew, fuel
MethodsEqual-λ, lambda iteration, QP, OPFPriority list, DP, Lagrangian relaxation, MILP
OutputSetpoints / λ (₹/MWh)On-off schedule for the day

Where it is used

Interview questions

Common mistakes

Related topics

Power system operation, SCADA and EMS · Electricity markets and regulation in India · Power generation: thermal, hydro, nuclear and renewable · Load flow and fault analysis · Smart grid and renewable integration · Power system stability.

Open in the Knowledge reader →Find jobs →