Knowledge / Electrical and Electronics Engineering / Transmission lines and cables

Transmission lines and cables

Electrical and Electronics Engineering (B.E./B.Tech) · Power systems · free study notes for exams, placements and interviews

In short

A transmission line carries bulk power from generating stations to load centres using four distributed parameters — series resistance and inductance, shunt capacitance and conductance. Because these are spread along the length, line behaviour is modelled by short, medium or long-line equivalents and by the ABCD two-port constants, which decide voltage regulation, efficiency and power transfer limits. Indian transmission runs at 66, 132, 220, 400, 765 kV AC (and ±800 kV HVDC), planned and operated by POWERGRID, state transcos and CTUIL under CEA and CERC rules. The topic is heavily examined in GATE EE (parameter calculation, ABCD, SIL, Ferranti effect) and in interviews at POWERGRID, NTPC, state boards, Sterlite, KEC, L&T, Siemens, Hitachi Energy and Tata Power.

Explained

Line constants: R, L, C and G

Line models: short, medium, long

ABCD constants and power transfer

Voltage regulation, Ferranti effect and compensation

Corona, travelling waves and insulation coordination

Underground cables for transmission and their comparison

Indian standards, practice and ratings

Key points

Formulas and examples

Inductance, single-phase two-wire line: L = (µ₀/π) ln(D/r′) H/m per loop; three-phase per phase L = 2 × 10⁻⁷ ln(Deq/GMR) H/m (D, Deq = spacing; GMR = 0.7788r for a solid conductor)
Capacitance (line to neutral): C = 2πε₀ / ln(Deq/r) F/m = 0.0242/log₁₀(Deq/r) µF/km (r = actual conductor radius, ε₀ = 8.854 × 10⁻¹² F/m)
Equivalent spacing of an unsymmetrical transposed line: Deq = (D₁₂ D₂₃ D₃₁)1/3
Short line: VS = VR + IZ; % regulation = (|VS| − |VR|)/|VR| × 100 (approximation valid when A ≈ 1)
Nominal π: A = D = 1 + ZY/2; B = Z; C = Y(1 + ZY/4); Nominal T: A = D = 1 + ZY/2; B = Z(1 + ZY/4); C = Y
Long line: A = D = cosh γl; B = ZC sinh γl; C = sinh γl / ZC; γ = √(zy); ZC = √(z/y) (z, y = series impedance and shunt admittance per km)
Surge impedance ZC = √(L/C) Ω; SIL = VL² / ZC MW (VL in kV line-to-line, ZC in Ω)
Lossless-line power transfer: P = VS VR sin δ / X MW (VS, VR in kV line-to-line, X in Ω, δ = load angle)
Ferranti voltage rise (lossless, per unit): (VR − VS)/VS ≈ (1/2) ω² L C l² = (1/2)(βl)²
Transmission efficiency η = PR / PS × 100 = PR / (PR + 3 I² R) × 100 for a three-phase line
Corona: Vd = 21.1 mo δ r ln(d/r) kV per phase (rms); δ = 3.92 b / (273 + t), b in cm Hg, t in °C
Travelling waves: reflection coefficient Γ = (Z₂ − Z₁)/(Z₂ + Z₁); refracted voltage = 2Z₂ V/(Z₂ + Z₁); v = 1/√(LC)
Cable: C = 2πε₀εr / ln(R₂/R₁) F/m; Emax = V / (R₁ ln(R₂/R₁)) V/m; dielectric loss = V² ωC tan δ

Example 1 — Inductance and capacitance of a transposed 220 kV line. Conductors of radius 1.0 cm are spaced 4 m, 4 m and 8 m. Find L and C per phase per km.

Example 2 — Short line: regulation and efficiency. A three-phase 33 kV, 20 km line has R = 0.2 Ω/km, X = 0.4 Ω/km and delivers 6 MW at 0.8 pf lagging at 33 kV.

Example 3 — Nominal π constants and the AD − BC check. A 150 km medium line: Z = 40 + j125 Ω, total Y = j1.0 × 10⁻³ S.

Example 4 — Surge impedance, SIL and loadability. A 400 kV line has L = 1.0 mH/km and C = 0.0112 µF/km.

Example 5 — Travelling wave at a line–cable junction. A 500 kV surge travels on an overhead line of ZC = 400 Ω into a cable of ZC = 50 Ω.

FeatureOverhead lineUnderground cable
InsulationAir (free, self-restoring)XLPE/paper — fixed, non-self-restoring
Capital costReferenceRoughly 4–10 times higher at EHV (varies with route)
Surge impedance250–400 Ω30–60 Ω
Charging currentSmallLarge — limits AC length
Fault location and repairVisible, hoursHidden, days; needs TDR/bridge methods
ExposureLightning, storms, treesDig-ups, moisture ingress, joint failure
Typical Indian useAll ISTS corridors, 66–765 kVMetro cities, 220/400 kV city feeds, crossings
ModelLengthShunt CB constant
Short< 80 kmNeglectedZ
Nominal T80–250 kmLumped at centreZ(1 + ZY/4)
Nominal π80–250 kmHalf at each endZ
Exact / long> 250 kmDistributedZC sinh γl

Where it is used

Interview questions

Common mistakes

Related topics

Overhead line design: sag, tension and insulators · Underground cables · HVDC transmission · FACTS devices · Load flow and fault analysis · High-voltage engineering and insulation

Open in the Knowledge reader →Find jobs →