Knowledge / Mechanical Engineering / Engineering economics and costing

Engineering economics and costing

Mechanical Engineering (B.E./B.Tech) · Industrial engineering · free study notes for exams, placements and interviews

In short

Engineering economics compares alternative technical choices in money terms over time — buy or lease, repair or replace, manual or automated — using interest, present worth, annual cost and rate of return. Costing is its companion: it works out what a product actually costs to make (material, labour, overhead) so a selling price, a quotation or a break-even volume can be defended. Both are examined in GATE ME (Industrial Engineering), in university Industrial Engineering and Engineering Economics papers, and in professional-body syllabi; they are also what cost accountants, production and project engineers at L&T, Tata Motors, BHEL, Maruti, ONGC, NTPC and every MSME tool-room actually use. Placement aptitude and technical rounds lean on break-even, payback, depreciation and simple interest-rate arithmetic. Indian practice adds GST, Companies Act depreciation and Income-tax Act block depreciation on top of the classical methods.

Explained

Cost concepts and classification

Ladder of costs and estimation

Overhead allocation, apportionment and absorption

Interest and the time value of money

Comparing alternatives and investment appraisal

Break-even, make-or-buy and value engineering

Key points

Formulas and examples

Prime cost = direct material + direct labour + direct expenses (₹)
Factory cost = prime cost + factory overhead; Cost of production = factory cost + admin overhead
Total cost = cost of production ± stock change + selling and distribution overhead; Selling price = total cost + profit
Machine-hour rate = total overhead of the machine (₹) / machine hours worked (h)
Material cost = volume (m³) × density (kg/m³) × rate (₹/kg) + scrap allowance − scrap credit
Contribution per unit c = s − v (₹/unit); BEQ = F / (s − v) (units); BE sales = F / (P/V ratio) (₹)
P/V ratio = (s − v)/s; Profit = Q(s − v) − F; Margin of safety = (actual Q − BEQ)/actual Q × 100 (%)
Simple interest F = P(1 + i·n); Compound amount F = P(1 + i)ⁿ; Present worth P = F / (1 + i)ⁿ
Effective annual rate = (1 + r/m)m − 1 (r = nominal rate/year, m = compoundings/year)
F/A: F = A[((1 + i)ⁿ − 1)/i]; A/F (sinking fund): A = F[i/((1 + i)ⁿ − 1)]
P/A: P = A[((1 + i)ⁿ − 1)/(i(1 + i)ⁿ)]; A/P (capital recovery): A = P[i(1 + i)ⁿ/((1 + i)ⁿ − 1)]
Capitalised cost (perpetuity) P = A / i; EUAC = (P − S)(A/P, i, n) + S·i + annual O&M
Straight line D = (P − S)/n; WDV D_t = r·B_{t−1}, r = 1 − (S/P)1/n; SOYD D_t = (P − S)·(n − t + 1)/[n(n + 1)/2]
Payback = first cost / annual net cash inflow (years); B/C = PW(benefits)/PW(costs)
i = rate per period (decimal), n = periods, P = present value (₹), F = future value (₹), A = equal annual amount (₹/yr), S = salvage value (₹), Q = quantity (units), F in break-even formulas = fixed cost (₹/period)

Example 1 — full cost sheet and selling price. A pump maker's month: direct material ₹4,80,000; direct wages ₹2,20,000; direct expenses (pattern hire) ₹20,000; factory overhead 60% of direct wages; administration overhead ₹75,000; selling and distribution ₹1,05,000; 2,000 pumps made and sold; profit at 20% of total cost.

Example 2 — machine-hour rate. A CNC turning centre costs ₹40,00,000, salvage ₹4,00,000 after 10 years, runs 2,000 productive hours a year. Annual costs: power 15 kW × 0.7 load × 2,000 h × ₹8/kWh; maintenance ₹1,20,000; operator ₹3,60,000; floor space and supervision ₹90,000. Interest on average investment at 10%.

Example 3 — break-even, margin of safety and a price cut. Fixed cost ₹18,00,000 a year; selling price ₹900/unit; variable cost ₹540/unit; present sales 7,500 units.

Example 4 — present worth, EUAC and payback for two machines. MARR 12%. Machine A: first cost ₹8,00,000, O&M ₹1,20,000/yr, salvage ₹80,000, life 6 years. Machine B: first cost ₹12,00,000, O&M ₹60,000/yr, salvage ₹1,50,000, life 6 years.

Example 5 — depreciation methods compared and a make-or-buy. Asset P = ₹10,00,000, S = ₹1,00,000, n = 5 years.

YearSLM D (₹)WDV D at 36.90% (₹)WDV book value end (₹)SOYD D (₹)
11,80,0003,69,0006,31,0003,00,000
21,80,0002,32,8393,98,1612,40,000
31,80,0001,46,9212,51,2401,80,000
41,80,00092,7081,58,5321,20,000
51,80,00058,4981,00,03460,000
MethodWhat it answersTime valueMain limitation
PaybackHow soon is money back?No (unless discounted)Ignores life after payback
ROIAverage accounting returnNoUses profit, not cash flow
PW / NPVRupee gain at MARRYesNeeds equal lives (LCM)
EUAC / AWAnnual cost of owningYesAssumes repetition of the cycle
IRREarning rate of the projectYesMultiple roots; poor at ranking
B/C ratioPublic-project worthYesBenefit/disbenefit classification is debatable

Where it is used

Interview questions

Common mistakes

Related topics