Knowledge / Mechanical Engineering / Production planning and control

Production planning and control

Mechanical Engineering (B.E./B.Tech) · Industrial engineering · free study notes for exams, placements and interviews

In short

Production planning and control (PPC) decides what to make, how much, on which machine, in what order and by when, then follows the shop floor to see that it actually happens. Planning converts a demand forecast into a master schedule, a capacity plan, routes and loads; control converts the schedule into dispatched work orders and corrects deviations through expediting. It is a heavily examined area in Industrial Engineering papers and in GATE ME (forecasting, line balancing, sequencing, scheduling) and is the daily job of planning engineers at Maruti Suzuki, Tata Motors, Ashok Leyland, Bosch, BHEL, HAL and L&T. Interviewers test it because it links design, manufacturing, costing and delivery performance in one decision.

Explained

What PPC is: objectives and functions

Production systems and planning horizons

Forecasting demand

Capacity planning, aggregate planning and the master schedule

Routing, loading, scheduling and sequencing

Line balancing and bottlenecks

Dispatching, control and current practice

Key points

Formulas and examples

Simple moving average: F(t+1) = (D(t) + D(t−1) + … + D(t−n+1)) / n — n = periods averaged
Weighted MA: F(t+1) = Σ wᵢ Dᵢ , Σ wᵢ = 1
Exponential smoothing: F(t+1) = α D(t) + (1−α) F(t) = F(t) + α e(t); 0 < α < 1, e(t) = D(t) − F(t)
Trend-adjusted (Holt): L(t) = α D(t) + (1−α)(L(t−1)+T(t−1)); T(t) = β(L(t)−L(t−1)) + (1−β)T(t−1); F(t+k) = L(t) + kT(t)
Seasonal index SI = average demand of the season / overall average demand; forecast = deseasonalised trend × SI
MAD = Σ|e| / n; MSE = Σe²/n; MAPE = (100/n) Σ|e/D| %; RSFE = Σe; Tracking signal = RSFE / MAD (limits ≈ ±4)
Utilisation = actual output / rated capacity; Efficiency = actual output / effective capacity
Input needed for one stage = required good output / (1 − scrap fraction); multi-stage: divide by the product of yields
Machines required N = (Q × t) / (H × E), Q = pieces to be made, t = time per piece, H = hours available per machine, E = availability × efficiency
Economic batch quantity EBQ = √[2 D Cs / (Ch (1 − d/p))] (batch sizing; the inventory note develops it)
Cycle time Cmax = available production time per period / units required; Takt time = same, set by customer demand
Theoretical minimum stations Nmin = ⌈Σ tᵢ / Cmax⌉ (round UP)
Line efficiency η = Σ tᵢ / (N × Cmax); Balance delay = 1 − η; Smoothness index = √[Σ (Cmax − tₛ)²]
Flow time Fᵢ = completion time Cᵢ − release time; Mean flow time = ΣCᵢ / n
Lateness Lᵢ = Cᵢ − dᵢ; Tardiness Tᵢ = max(0, Cᵢ − dᵢ); Makespan = time from start of first job to finish of last
Critical ratio CR = (due date − present date) / remaining processing time; Slack = due date − present date − remaining processing time
Little's law: WIP = throughput rate × average flow time
Learning curve: T(n) = T(1) × nb, b = log r / log 2 (r = learning rate, e.g. 0.8 for an 80% curve)

Example 1 - Exponential smoothing with an error check. Demand (units/month): 1,100; 1,050; 1,200; 1,150. Forecast for month 1 was 1,000, α = 0.2.

Example 2 - Machine requirement and utilisation. 60,000 good gear blanks a year; machining time 4.5 min/piece; scrap 4%; plant works 300 days, two 8-hour shifts; machine availability × efficiency = 0.85.

Example 3 - Assembly line balancing. Tasks (seconds): A 25, B 30, C 20, D 35, E 15, F 40, G 25, H 30 (Σ = 220 s). Precedence: A first; B and D after A; G after B; E and F after D; C after G; H last. Required output 450 units in a shift of 450 productive minutes.

Example 4 - Johnson's rule (5 jobs, turning then grinding, hours).

JobM1 turningM2 grinding
A52
B16
C97
D38
E104

Example 5 - SPT versus EDD on one machine (days).

JobProcessing timeDue date
146
224
3618
438
5512
AspectJob productionBatch productionMass / flow production
LayoutProcessProcess or cellProduct (line)
PPC difficultyHighest (every order unique)Medium (lot sizing + sequencing)Low after balancing
Key PPC toolGantt chart, priority rulesEBQ, MPS, CRPLine balancing, takt, kanban feed
WIP and lead timeHigh, variableModerateLow, predictable
Indian exampleL&T heavy fabricationPump and valve makersMaruti Manesar, TVS Hosur

Where it is used

Interview questions

Common mistakes

Related topics

Inventory control and MRP · Work study and ergonomics · Lean manufacturing and Six Sigma · Operations research basics · Engineering economics and costing · Maintenance and reliability engineering