Knowledge / Mining Engineering / Mine development and shaft sinking

Mine development and shaft sinking

Mining Engineering (B.E./B.Tech) · Mining methods · free study notes for exams, placements and interviews

In short

Mine development is all the work that opens a deposit and connects it to the surface — shafts, inclines, adits, declines, levels, raises and winzes — before and alongside production. Shaft sinking is the costliest, slowest and most hazardous part of it: a 500 m coal shaft in India takes one to two years and runs into hundreds of crores when lining, headgear and winding are counted. The subject is examined in every mining-engineering degree under Mining Methods and in GATE (Mining, MN) under development, and is daily work at Coal India subsidiaries (ECL, BCCL, CCL, SECL, WCL, MCL, NCL), SCCL, Hindustan Zinc, Hindustan Copper, Uranium Corporation, NMDC, Tata Steel and contractors such as CMPDI-designed projects executed by Thyssen/Shaft Sinkers-type specialists.

Explained

What "development" means and the openings used

Choosing and designing the entry

Ordinary (conventional) shaft sinking — the cycle

Used where strata are reasonably firm and water inflow is manageable by pumping.

  1. Site preparation and pre-sink: clear site, build foundations, sink the top few metres (fore-shaft/collar) by hand or excavator, build the permanent concrete collar and install the sinking headgear, winch/winder, kibble, cactus grab and sinking stage.
  2. Drilling: a multi-boom jumbo or jackhammers on an air-leg drill the round from the sinking platform; hole depth typically 1.5-4 m, with a wedge/pyramid/burn cut at the centre so the round throws rock inwards.
  3. Charging and blasting: cartridge explosives (slurry/emulsion) with delay detonators; centre cut first, then easers, then perimeter; permitted explosives and shot-firing rules apply in coal.
  4. Fume clearance and ventilation: forcing auxiliary fan with a duct ending a few metres above the bottom; no re-entry until the atmosphere is tested.
  5. Dressing and mucking: loose rock barred down; muck loaded by cactus grab (clamshell) or excavator into kibbles and wound to surface; this is usually the longest step.
  6. Lining/walling: concrete placed behind shuttering, either continuously a few metres above the bottom or in sets from a walling crib; temporary support (rings, shotcrete, rock bolts) where lining lags.
  7. Dewatering: sinking pump in the bottom or a staged pumping arrangement; water is the single biggest cause of lost sinking time.
  8. Typical performance: one or two rounds per shift cycle, giving roughly 1.5-3 m/day overall advance in good ground; far less if water, bad ground or lining delays intervene.

Special methods of shaft sinking

Used when ordinary sinking cannot cope with water or running ground.

Lining, equipment and shaft fittings

Safety, law and Indian practice

Key points

Formulas and examples

Excavated shaft volume V = (π/4) D_ex² H, with D_ex = D_f + 2t
D_ex = excavated diameter (m), D_f = finished (clear) diameter (m), t = lining thickness (m), H = depth (m), V in m³
Lining concrete volume V_L = (π/4)(D_ex² − D_f²) H (m³)
Powder factor PF = mass of explosive / volume of rock broken (kg/m³); specific drilling = total drilled metres / m³ broken
Advance per round (pull) a = η_p × l, where l = hole depth (m), η_p = pull efficiency (0.8-0.9)
Sinking rate = a × (rounds per day); time to sink = H / rate (days)
Lining thickness, external pressure only (Lamé, thick cylinder) b = a √[σ / (σ − 2p)], t = b − a
a = inner radius (m), b = outer radius (m), p = external ground/water pressure (MPa), σ = permissible compressive stress of lining (MPa)
Ground pressure estimate p = γ H (sometimes reduced by arching/Protodyakonov); γ = unit weight of overburden (kN/m³ → MPa by ÷1000)
Static winding load W = (m_payload + m_cage + m_rope) g; rope factor of safety FoS = breaking load / static load
Accelerating force F = m (g + f), f = acceleration (m/s²)
Winder power (balanced) P = (net load × g × v) / η_m ; v = rope speed (m/s), η_m = mechanical efficiency
Pump power P = ρ g Q H_t / η ; ρ = 1000 kg/m³, Q = m³/s, H_t = total head (m), η = overall pump efficiency
Ventilation quantity Q = A × v ; A = shaft cross-section (m²), v = air velocity (m/s)

Example 1 — quantities for a 500 m shaft. Finished diameter 6.5 m, concrete lining 450 mm, depth 500 m.

Example 2 — sinking time. Hole depth 3.0 m, pull efficiency 85%, 0.9 complete cycles per day.

Example 3 — lining thickness by Lamé. Clear radius a = 3.25 m, design external pressure p = 0.8 MPa, permissible compressive stress of concrete σ = 7 MPa (M30 with a factor of safety about 4).

Example 4 — winding rope check and power. Payload 8,000 kg, cage 5,000 kg, rope 5.6 kg/m over 500 m, rope breaking load 1,400 kN, hoisting speed 10 m/s, acceleration 0.8 m/s², balanced winder with tail rope, η_m = 0.90.

Example 5 — dewatering cost during sinking. Inflow 1,200 litres/min, total head 520 m, pump-and-motor efficiency 70%, tariff ₹7/kWh.

MethodGround suited toRelative costSpeedKey limitation
Ordinary sinkingFirm rock, modest waterLow1.5-3 m/dayStops in heavy water/running ground
CementationFissured water-bearing rockLow-mediumAdds pre-grouting timeWill not seal fine-pored or flowing sand
Ground freezingThick wet sands, alluviumHighMonths of pre-freezeRefrigeration plant, must hold till lining done
Piling / caissonShallow soft wet coverMediumSlowOnly tens of metres deep
Blind shaft boring (SBM/VSM)Uniform strataVery highCan exceed 3-4 m/dayDiameter and depth limits, capital
Raise bore + slashNeeds an existing lower levelMediumFastNot possible for the first shaft
Entry typeCapitalHoisting costVentilationTypical Indian use
AditLowestNil (self-draining)EasyHilly terrain, NE coalfields
InclineLow-mediumConveyor, cheap per tonneModerateShallow coal seams
Decline/rampMediumTrucks or conveyorNeeds more airMetal mines, trackless equipment
Vertical shaftHighestLowest per tonne at depthBest (least resistance)Deep coal and metal mines

Where it is used

Interview questions

Common mistakes

Related topics

Surface mining methods · Underground coal mining · Underground metal mining · Mine ventilation and air conditioning · Rock mechanics and ground support · Mine hoisting and winding · Drilling and blasting technology · Mine legislation and safety (DGMS)

Open in the Knowledge reader →Find jobs →