Knowledge / Mining Engineering / Underground metal mining

Underground metal mining

Mining Engineering (B.E./B.Tech) · Mining methods · free study notes for exams, placements and interviews

In short

Underground metal mining is the extraction of metalliferous ore bodies (lead-zinc, copper, gold, uranium, manganese, chromite) by driving openings in rock and removing ore from excavations called stopes, with the overlying rock either supported, backfilled or deliberately caved. The method is chosen from ore geometry, dip, ore and wall rock strength, grade distribution, depth and subsidence tolerance - not by preference. It matters because India's base-metal and gold reserves are deep and steeply dipping, so surface mining is not an option: Hindustan Zinc's Rampura Agucha, Sindesar Khurd, Rajpura Dariba and Zawar, HCL's Malanjkhand and Khetri, UCIL's Jaduguda and Narwapahar, and Hutti Gold Mines all run underground. It is a high-weight area in GATE Mining (MN), in UPSC/state Mines Inspector and DGMS statutory competency examinations, and in campus interviews for Hindustan Zinc, Vedanta, Hindustan Copper, UCIL, NMDC, Tata Steel, SCCL and mining contractors such as Barminco, Byrnecut and Thriveni.

Explained

Terminology and the classification of methods

Room-and-pillar (flat to gently dipping deposits)

Stoping methods for steeply dipping ore bodies

Method selection, design and rock mechanics

Unit operations, services and productivity

Indian regulation, standards and practice

Key points

Formulas and examples

Dilution (%) = (waste tonnes mined / ore tonnes mined) × 100; Dilution factor = (ROM tonnage − ore tonnage)/ore tonnage
Diluted grade g_d = (T_o × g_o + T_w × g_w) / (T_o + T_w) [T in tonnes, g in % or g/t; waste grade g_w often 0]
Ore recovery (%) = (ore tonnes drawn / ore tonnes in situ) × 100; Mine call factor = metal in mill feed / metal estimated in situ
Tonnage of a block T = L × W × H × ρ [m × m × m × t/m³ = t; ρ = in-situ bulk density]
Swell factor = loose volume / in-situ volume; Bulking (%) = (swell factor − 1) × 100
Tributary-area pillar stress σ_p = σ_v × (w_p + w_o)² / w_p² (square pillars); σ_v = ρ g H ≈ 0.027 H MPa for ρ = 2,700 kg/m³, H in m
Extraction ratio e = 1 − w_p² / (w_p + w_o)²; Pillar factor of safety FoS = pillar strength S_p / σ_p
Obert-Duvall pillar strength S_p = S₁ (0.778 + 0.222 w/h) [S₁ = strength of a cubical specimen, w/h = width-to-height ratio]
Hydraulic radius HR = A / P [stope face area ÷ its perimeter, m]; Stability number N' = Q′ × A × B × C
Powder factor PF = kg explosive / tonne broken (or kg/m³); Specific drilling = drilled metres / tonne broken
Development ratio = metres of development / 1,000 t of ore reserve accessed
MethodDip / shapeOre & wall strengthRecoveryDilutionRelative costProductivity
Room-and-pillarFlat, < ~30°, tabularStrong ore, competent roof50-80%LowLowHigh
Shrinkage stopingSteep, narrow, regularStrong ore and walls70-85%Low-moderateModerateLow
Sublevel stopingSteep, thick, regularStrong ore and walls75-90%5-15%LowVery high
VCR / VRMSteep, thick, regularStrong ore75-90%5-15%LowVery high
Cut-and-fillAny dip, irregularWeak to moderate90-98%< 5-10%HighModerate
Sublevel cavingSteep, thick, largeAny ore; caving HW70-90% drawn15-35%LowVery high
Block cavingMassive, large footprintCavable, fragmenting> 90% of block10-25%LowestHighest
Fill typeCompositionTypical UCSMain role
Dry rock fillDevelopment wasteNegligibleWall confinement, waste disposal
Hydraulic sand fillDeslimed tailings slurry0.2-1 MPa (if cemented)Floor and wall support, drained
Paste fillFull tailings 75-85% solids + 3-7% cement0.5-4 MPaPillar recovery, free-standing faces
Cemented rock fillWaste rock + cement slurry3-8 MPaSills, undercuts, exposed fill walls

Where it is used

Interview questions

Common mistakes

Related topics

Open in the Knowledge reader →Find jobs →